325 Binney St developer logo

September 2018 - February 2020

Community Meetings

Beginning in the Fall of 2018 and stretching through February 2020, we attended more than 30 community meetings to discuss revised plans for the project. Presentation included the Linden Park Neighborhood Association, East Cambridge Planning Team, Cambridge Redevelopment Authority and the East Cambridge Business Association.

September 2019

Filed Zoning Petition

Third filing of the Grand Junction Pathway Overlay Rezoning Petition

November 2019

Planning Board Presentation

325 Binney St rezoning presentation at the Planning Board. Positive recommendation granted by the Planning Board.

December 2019

Ordinance Committee Meeting

325 Binney Street re-zoning presentation at the Ordinance Committee.

January 2020

ECPT Meeting

325 Binney Street rezoning presentation at the East Cambridge Planning Team meeting.

February 2020

Ordinance Committee Meeting

325 Binney Street re-zoning presentation at the Ordinance Committee. Referred out of committee and back to the full council for consideration.

March 2020

Grand Junction Pathway Overlay Zoning Passage

Cambridge City Council meeting where Grand Junction Pathway Overlay Zoning passed with a 9-0 affirmative vote.

July 8, 2020

ECPT Meeting

Presented the building design at a virtual ECPT meeting.

Jul, 15, 2020

Virtual 325 Binney Street Open House

325 Binney Street building design will be presented.

October 20, 2020

Planning Board

Special Permit and Design Review of building and site plan.

November 2020

November 2020

Site Work Start

Feb, 03, 2021

Neighborhood Update

Construction and Geothermal Update

March 2021

Construction Start

Construction Start